Phase Timeline
Phase Overview
Critical Path
The critical path runs Phase 0 → Phase 1 → Phase 2 → Phase 3 → Phase 5 → Phase 6 → Phase 7 → Phase 8. Phase 4 and Phase 9 sit on parallel branches. Phase 4 must complete before Phase 5’s evaluation integration. Phase 9 is strictly optional and gated on enterprise readiness.Quality Gates
Each phase ends with a formal quality gate:- Documentation completeness: spec coverage above 80%
- Test traceability: every requirement linked to a test case
- Benchmark integrity: no regressions on the Optimization Set
- Security review: artifact signing and dependency audit
Phase timing assumes a six-person core team with access to A100-class GPUs. Delays in GPU procurement or benchmark licensing will shift the timeline.
Success Metrics
- Phase 0-3: All specs written, all tasks in DONE state
- Phase 4-5: First evolved candidate produced with PASS status
- Phase 6-7: Sub-100ms inference latency on target hardware
- Phase 8: Enterprise customer sign-off on offline deployment
- Phase 9: RAG pipeline integrated with InferenceBackend